Delay Meter by MGR

£0
lost to delay so far
£0per day
£0per hour
£0per minute
£0per second
Funding runs out in
—days
00 h 00 m 00 s
Set the allocated funding to start the countdown
Allocated £0Released at gates £0Cash left £0
£0cost of each day late
0days on the cost clock
—next payment gate
0days to revised target
—target in service

The problem and the clock

When does the delay start costing, and when should the fix be in service?

Daily cost lines

Everything that burns money for every day the fix isn't in service. Change any number and the meter recalculates.

Cost lineTypeQty£ per unit/day£/dayFunded
Daily burn today£0

Bad days log

Log any day that hurt the project. Assets out are priced at the rate above.

DateWhat happenedTrains outOther £Day cost
Bad days total£0

Privacy

Use codes instead of real names in the template. The real names, and any scale factor that hides the true figures, sit in your key. The key stays on this computer and is never saved with the project or shared.

Load my key

Funding

The money allocated to the project. The countdown spends it at the daily rate of every cost line ticked “Funded”, plus extra daily costs from changes.

Against the baseline

No baseline yet. Set one to track how the project moves.

—total cost change
—daily burn change
—target date change

Project bill

Capital cost of the fix
Changes: one-off costs£0
Delay cost to date£0
Bad days logged£0
Further delay cost to revised target£0
Total if delivered on revised target£0
A
On the line

Depot and railway

What obsolescence costs the depot while it waits for the fix. These costs stop when the fix is in service, so delay makes them bigger.

Where the money goes

Daily burn by type.

What if?

Drag to bring the in-service date forward or push it back.

On target£0

Changes and new findings

Anything found along the way, such as new scope, a design change or a supplier slip. Give each one a one-off cost, any extra daily cost and the days it adds to the timeline. Untick an item to see the project without it.

Quick add:
FoundChangeTypeOne-off £Extra £/dayDelay daysPaid byGrowth %/monthIncludeTotal impact
Changes total£0

Total impact = one-off cost + the extra daily cost from the date found until the fix is in service (growing at its monthly rate) + the delay days charged at the full cost of being late. “Paid by Depot” keeps a cost out of the project funding but in the project’s total impact.

Supplier payment gates

The supplier is paid in stages. Each gate’s payment is held until the gate is passed, then the money is released. Held money still counts as committed against the funding, and the countdown pays each gate on its planned date.

GatePayment £Planned dateStatusDate passedTiming

Failed a gate? Set it to “Failed: re-review”, move the planned date, and add the slip as a change so the target date moves too.

This is a made-up sample project (Northbridge Rail). Download a template to track your own.